A Barrett company - serving Arlington, TX

How Long Does a Home Renovation Take? (Arlington, TX)

Home additions & ADUHome additions & ADU
Kitchen remodelingKitchen remodeling
Bathroom remodelingBathroom remodeling
RoofingRoofing
Windows & doorsWindows & doors
Driveway & paversDriveway & pavers
FenceFence
Every visit starts with

Free written scope consultation - allowances, timeline, and change-order rules on paper before a single trade is scheduled

We have financing partners for your dream remodel*On approved credit; ask us about your options
Get your free estimate
Explore

Styles & brands we work with

  • Kitchen remodeling
  • Bathroom remodeling
  • Home additions & ADU
  • Roofing
  • Windows & doors
  • Driveway & pavers
  • Fence
Before & after

See the difference

Before - Recent ProjectBeforeAfter - Recent ProjectAfter
Recent Project
Before - Full RestorationBeforeAfter - Full RestorationAfter
Full Restoration
Before - Complete UpgradeBeforeAfter - Complete UpgradeAfter
Complete Upgrade

Here is the HTML content for the page, written to the specifications provided.

How long does a home renovation take in Arlington, TX?

A small kitchen remodel in Arlington usually takes 6 to 10 weeks, while a full home addition runs 4 to 7 months. The exact timeline depends on scope, permit speed, and one local factor most estimates ignore: the spring hail surge. If you sign a contract in April, May, or June, plan for 3 to 6 extra weeks. Storm season books every electrician, roofer, and window installer in Arlington on insurance rebuilds, and your job waits in line behind them.

Here’s what that looks like in practice. A kitchen that takes six weeks in January can stretch to eleven if you sign the week after a quarter-sized hail event. We’ve seen it happen more than once. When the phone rings for a renovation in Arlington, we check the calendar before we check the scope. Call (888) 590-9867 and we’ll tell you honestly where the schedule stands.

Arlington-specific timelines for common projects

The ranges below assume a typical 1990s-2000s south Arlington subdivision or a 1950s-70s brick ranch in central or east Arlington. They are realistic, not salesman-short. Every project has its own surprises, but these are the numbers we work from.

Project type Typical duration Notes
Small kitchen remodel 6-10 weeks Cabinet install and countertop lead times are the long poles. KraftMaid and Cambria orders can take 3-5 weeks to arrive.
Full kitchen remodel 8-16 weeks Add layout changes or moving plumbing and you’re on the high end.
Bathroom remodel 3-6 weeks A tub-to-shower conversion is usually faster than a full layout change.
Home addition 4-7 months Permit time plus foundation work on Blackland Prairie clay can push this to 8 months.
ADU construction 5-9 months Site prep and separate utility runs add weeks.
Roof replacement 1-3 days Weather permitting. Spring hail season can delay start dates by weeks.

Notice the pattern? The bigger the foundation and permitting footprint, the more Arlington’s clay soil and Development Services timeline matter. We’ll get to both.

The hail surge modifier: why a May start costs you weeks

Arlington sits in the DFW hail belt. When a storm rolls through in April or May and drops quarter-sized stones across south Arlington, every local contractor pivots to insurance-driven roof and window rebuilds. That’s not a complaint. It’s the reality of construction here. The subs on your renovation are the same people handling storm claims for hundreds of other homeowners.

What does that mean for your schedule? The permit inspector might still show up on time, but your electrician, your drywall crew, and your cabinet installer are juggling three jobs. They’re not bad at what they do. They’re stretched. A renovation started in October, after the storm season settles, moves faster and with fewer interruptions. If you can schedule around the hail calendar, do it. If you can’t, build the buffer into your expectations.

Barrett & Sons doesn’t chase storm work and abandon renovation clients. Tom and his sons stay on the renovation schedule. That’s one reason we aim to book kitchen and bath projects before or after the spring rush.

Arlington permit timelines: the clock starts with drawings, not handshakes

Arlington Development Services typically takes 10 to 15 business days to review a residential addition permit. That clock does not start when you sign a contract. It starts when complete drawings land on their desk. Contractors who skip pre-planning, show up on demo day without a permit submitted, and then discover the wait add weeks before the first hammer swings.

We submit drawings early. Every eligible job includes permits pulled and inspections signed. That’s not a marketing line. It’s the difference between a four-month addition and a six-month addition. The permit inspector works for you, not for us. That’s why we like him.

What happens when walls open in a 1990s south Arlington home

Arlington’s housing stock is a patchwork. Central and east Arlington hold 1950s-70s brick ranches with original single-pane windows and pier-and-beam or early slab foundations. South and far north Arlington are full of 1990s-2000s subdivisions. When you open walls in a 1990s home for a kitchen or bath remodel, the electrical and HVAC you find often doesn’t meet current code. Bringing it up to code adds 1 to 2 weeks most estimates don’t mention.

We plan for it. Our technicians have up to 28 years of experience, and they’ve opened enough walls in Arlington to know what’s behind them. American Standard and Toto fixtures, Schluter waterproofing, Sterling shower surrounds: we install the premium brands because they hold up. But the schedule protection comes from written change orders before any scope change touches the job. An allowance that isn’t on paper is a surprise waiting for a date. When a homeowner runs out of budget mid-project because the allowance didn’t cover reality, work stops. We don’t let that happen. Every price change arrives in writing before a single nail moves.

There’s also the Blackland Prairie clay. It swells and shrinks with the seasons, and after a dry summer followed by a wet fall, slabs crack. If your addition or kitchen remodel starts with foundation work, plan an extra week for assessment and for bringing any slab movement up to spec before framing.

Why the schedule slips on national jobs (and how we avoid it)

The hidden schedule-killer on large renovations isn’t materials. It’s communication. When a national company runs a job through a project manager who’s never met the sub, instructions get relayed, misunderstood, and re-sent. The electrician waits for the framer who waited for the drywall delivery that was ordered two days late. Meanwhile, Tom Barrett and his sons are on-site most days. Not every day on every job, but often enough to catch a delay before it becomes a week.

We’re owner-operated. Founded in 1998, Barrett & Sons Construction has been pulling permits and standing behind the work for 29 years. When something’s wrong, you call and Tom comes back. The 90-Day Done Right Promise is written on every contract. One call brings him back. That’s how we protect both the schedule and the finish.

If you want to know more about how we handle a specific project, visit our home page for the full scope of what we do.

FAQs

Need Construction help in Arlington? Licensed & insured · free written estimates
Call (888) 590-9867
Local Service Coverage

Request a Free Estimate in Arlington

Tell us what you need - Barrett & Sons Construction Arlington responds fast. No obligation.

By submitting this form you agree to our Privacy Policy and consent to be contacted by phone, email or SMS about your request, including by local professionals who may handle it.

Call Now - 24/7 Dispatch